From four lanes to two, now the construction sites: ten million for the roundabout and the Croce railway overpass
Croce area | The areas of the two construction sites have been handed over to the companies
cavalcaferrovia Crocerondò Croceviabilità

From four lanes to two, now the construction sites: ten million for the roundabout and the Croce railway overpass

3.8 million for the roundabout and 6.2 for the first lot of the bridge. But the full bill is 14.6: there is still no money for the deck

📅giovedì 3 settembre 2026
✍️@A_Lex

📸 Gallery

Anyone entering Taranto from the west has known since late April: on the Croce overpass, traffic runs on two lanes instead of four, and during rush hour the queue starts well before the bridge. As of this morning, at least, there is a real construction site under that bottleneck: the Municipality has handed over the areas of the roundabout and the railway overpass in the Croce area to the contracting companies. Ten million euros in total, work starting in the coming days.

At the handover, reports TarantoToday, the mayor Piero Bitetti, the councillor for Public Works Lucio Lonoce, and the chief of staff Maria Lucia Venneri were present. «We are unblocking a fundamental intervention for the traffic flow at the entrance and for the image of Taranto — said the mayor — above all, we are restoring the safety conditions of these infrastructures.» The stated goal is to finish by the end of the year.

Where we are, and why that node matters

The most accurate description of the two interventions is in the Municipality's documents, and it is less bureaucratic than one might expect. The roundabout is «the interchange located at the entrance to the city of Taranto, near the industrial area», the one that «connects the traffic flows converging from the SS106 and SS7 arteries» and directs them towards the local road network in the direction of the Tamburi district. The railway overpass is «the overpass that runs along the road to Massafra», the bridge that crosses the railway and «allows the connection, in both directions, of the city with the industrial plants located there and with the SS7».

In short, it is the gateway through which one enters and exits from the side of the industrial area: commuters from the northern districts, vehicles heading to the plants and the port, and trucks heading up to the state highway all pass through here. It is not a neighborhood detail: in the list of critical nodes for the Ionian road network, the roundabout and the railway bridge of Taranto Croce have long been indicated as black spots, together with the intersection of state highways 7, 100, and 106.

On the bridge, in addition to the rehabilitation of the pillars, «the improvement of the safety of the overlying road platform is planned, through the replacement of existing guardrails and pedestrian restraint barriers».

The two lanes of April, and the reason why

The narrowing did not start with the works: it came first, as a safety measure. On April 24, 2026, the city hall announced that from April 26 the carriageway of the overpass would go «from 4 to two lanes», following «surveys and analyses carried out on the structure». The Municipality's note used clear words: it is «a public safety intervention due to the conditions of degradation found on some structures that could compromise their load-bearing capacity». And again: «It is, in fact, a risk management measure that reduces the probability of harmful events».

Translated: the checks had found enough to recommend lightening the bridge, pending static and seismic consolidation. That halving of lanes remained in effect throughout the summer.

Ten million on the table, but the bill is fourteen

The money comes from the Puglia Region: ten million under the POC Puglia 2014-2020, Axis VII, the chapter dedicated to transport and accessibility to strategic nodes — the SS106, the SS7, the second front of the station, the port, and the logistics platform. The breakdown is as follows:

  • 3.8 million for the safety upgrade of the Croce roundabout and its entry and exit points;
  • 6.2 million for the first lot of extraordinary maintenance of the railway overpass, intended for the static rehabilitation of the pillars and the improvement of the road platform.

Here, however, the fine print must be read. The design directive document, approved by the Municipal Council on May 22, 2026, divides the bridge's recovery into three functional lots, and the first is indeed just the first:

  1. Lot 1 — extraordinary maintenance of the road and substructure: 4,155,347.92 euros of works, within a financial framework of 6.2 million. This is the one funded and just handed over.
  2. Lot 2 — completion of interventions on the substructure: 1,895,724.58 euros.
  3. Lot 3 — seismic improvement and rehabilitation of the deck: 8,594,094.03 euros. This is the most expensive, and it concerns the surface on which one walks and drives.

Sum of the three: over 14.6 million for works alone. The regional allocation is ten million, and it also includes the roundabout. As Voce del Popolo noted while reconstructing the documents, the numbers do not add up: for the second and third lots, to date, there is no coverage. This morning's construction site restores the foundations and the road; the deck and seismic improvement remain an item without funding.

Who will do the work, and how much they discounted

The two tenders were closed within four days, using the same formula: negotiated procedure without a call for tenders, invitations from the Municipality's supplier register, award to the lowest price, bids to be submitted by August 27. The names and numbers are in the determinations published on the Albo Pretorio in recent days.

  • Railway overpass, lot 1 — awarded to C. Costruzioni srl of Potenza with a discount of 21.322%: from a tender base of 4,229,648.92 euros (of which 246,612.91 euros for safety costs, not subject to discount) to a contractual amount of 3,380,385.98 euros plus VAT. Determination no. 6285 of August 31, published on September 1.
  • Croce roundabout — awarded to the grouping of Impresa Ottomano ing. Carmine srl (lead company) and S&C Costruzioni srl (subsidiary), both from Taranto, with a discount of 30.966%: from a base of 2,886,546.36 euros to 2,013,678.51 euros plus VAT, for a total commitment of 2,456,687.78 euros. Determination no. 6331 of September 1, published on the 2nd.

This amounts to just under 5.4 million euros in contracted works against the 10 million allocated: the savings from the tenders remain in the financial frameworks and, by law, are not savings to be taken away but a reserve on which the entity can decide. It should be noted that we are still at the proposal of award: it becomes effective only after verification of the companies' requirements, which is still ongoing. Precisely for this reason, both determinations order the urgent handover (art. 17, paragraphs 8 and 9 of the contracts code), to «avert the serious damage to the public interest that would result from the failure to execute the contract». Translated: the schedule is tighter than the checks.

Who signs, who designs

The process went through the summer. With determination of the Directorate of Public Works and Infrastructure no. 595 of July 15, 2026, the Municipality reorganized the figures of the procedure: the sole project manager remains the architect Elena Campocci, the project verification is entrusted to engineers Alessandro Zito and Simona Abatematteo with technical officer Cinzia D’Eredità, the tender phase to Giuseppe Casamassima with Roberta Lippolis.

Five days later, on July 20, the same directorate awarded the executive design and safety coordination during the design phase of the first lot to Infratech Consulting S.r.l. for 129,417.60 euros. The measure states that, «in consideration of the urgency of the maintenance interventions», the service was handed over urgently, while checks on requirements were still ongoing. A bureaucratic detail that says how little margin there was.

The regional funding had been deliberated by the Council of Antonio Decaro on July 3. It was announced by regional councillor Cosimo Borraccino, who spoke of «particularly significant» works and linked them — like almost everything this year — to the appointment of the Mediterranean Games.

Under the bridge there are shops

During the months of the narrowing, the area paid a price that administrative documents do not record. Francesco Battista, of Futuro Nazionale, had requested a public timeline in July — date of the tender, opening of the construction site, full reopening of traffic — pointing a finger at the commercial activities in the area: «For months, the road closure and access difficulties have inevitably reduced customer traffic», with «a significant decrease in revenue». The merchants of the roundabout, reports Antenna Sud, have even considered legal action over the isolation of the area.

The discontent is broader than the single construction site. At the end of April, the vice-president of the Regional Council Renato Perrini had requested an urgent hearing in the Transport Commission on the entire Ionian infrastructure system, indicating precisely the Croce roundabout and the nearby railway bridge among the points to be resolved, and recalling that the Northern bypass — the one that should connect the SS106, the Punta Penna bridge, and the southern bypass — is stalled and unfinished. Around the same time, Adiconsum Taranto-Brindisi, with president Gianfranco Solazzo, spoke openly of «collapse» due to the construction sites open in multiple points of the city.

What changes now for drivers

Little, in the immediate term, and it is worth knowing: the narrowing to two lanes had been ordered until the completion of the static and seismic consolidation works, so it remains. With the opening of the construction sites, it is reasonable to expect new signage and further specific restrictions on the roundabout and ramps: at the time of publication, the Municipality has not released a new traffic plan beyond the one from April.

For those arriving from the north who do not need to cross the node, the alternative remains to move onto the main routes outside the city before re-entering; for those moving within Taranto, the urban lines of Kyma Mobilità remain, and in the future the BRT should lighten precisely the corridors that are currently congested.

Regarding the deadline, it is worth doing the math, because it is tight. The specifications set 120 calendar days from handover as the time limit for completing the works: starting from September 3, this leads to the first days of January. But the funding is a POC 2014-2020, and those programs expire on December 31, 2026; the specification for the railway overpass states it in black and white — the execution «must guarantee the completion of the works in a perfectly workmanlike manner by December 2026». Four net months, without margin, on two construction sites open simultaneously on the same node.

And this still concerns only the first piece of a longer game: once the pillars and the road platform are secured, funding for the deck will still need to be found. In the meantime, the practical advice is the usual one when a construction site opens on an entrance gateway: check the ordinances before hitting the road, and allow for a few extra minutes.

Photo: Carlos Delgado (CC BY-SA 3.0), ParisTaras (CC BY-SA 4.0) and Giov.c (public domain), Wikimedia Commons.

#cavalcaferrovia Croce#rondò Croce#viabilità#lavori pubblici#Comune di Taranto#Regione Puglia#POC Puglia#statale 106#mobilità#Piero Bitetti

Share

💬

Commenti sulla notizia

0/2500

Potrebbero interessarti