New cables under seventeen streets: the construction site schedule from Tre Carrare to the Borgo
Works | Power grid
lavorirete elettricaTre Carrare

New cables under seventeen streets: the construction site schedule from Tre Carrare to the Borgo

Until the end of March, a new medium-voltage underground line: digging one street at a time, on weekdays from 7 AM to 5 PM

📅domenica 11 ottobre 2026
✍️@A_Lex
🎧 Ascolta l'articolo3:13
Velocità

📸 Gallery

You can't see it, but it's what keeps the lights on in homes. Under the streets between Tre Carrare, Solito, and the Borgo, a new medium-voltage underground power line is about to be laid: it will strengthen the grid and improve service. To install them, the asphalt has to be opened, and the construction site will move one street at a time, from now until March 31.

The work is being done by the company Giannone Group, with authorization from the City's Public Works department. The rules are the same at every stage: work takes place on weekdays from 7 AM to 5 PM, with a no-parking ban on both sides and vehicle removal. Where the road narrows too much, traffic will alternate in a single lane, with workers or a traffic light. In the evening, on Saturdays, and Sundays, parking returns to normal.

First stage: from via Caduti di Nassiriya to corso Italia

It starts until October 22 on via Caduti di Nassiriya, from number 9 to corso Italia. Then, from October 23 to December 4, it's the turn of corso Italia, in two sections: between via Liside and via Japigia, and between via Marche and via Caduti di Nassiriya. The BRT construction site is already on corso Italia, and the City has set a precise condition: the half of the roadway occupied by the new bus line work is not to be touched.

December and January: the streets of the regions

From December 7 to 17, digging takes place on via Marche, between via Umbria and corso Italia. December 18 is the turn of via Toscana, December 21 and 22 of via Umbria. Then, for the holidays, there are no dates: the schedule resumes after Epiphany.

In January: via Capitanata on the 7th and 8th, via Calabria from the 11th to the 15th, via Vaccarella from the 18th to the 20th, via Tirrenia on the 21st and 22nd, via Liside from the 25th to the 29th.

February and March: towards the Borgo

Via Capecelatro on February 1st and 2nd, via Messapia from the 3rd to the 12th, via Temenide from the 15th to the 19th, via Leonida on the 22nd and 23rd, via Minniti from February 24th to March 3rd. On via Leonida and via Minniti, the BRT rule also applies: the half of the road used by buses remains clear.

The last long stage is via Dante, between via Cavallotti and via Minniti, from March 4 to 26. It closes on March 30 and 31 on via Cavallotti.

What lies beneath

A curiosity for those passing through via Marche in December. This is the neighborhood built above the great necropolis of Greek Taranto, and right on via Marche there is an archaeological area where chamber tombs and sarcophagi can be seen, with small vases left beside the dead. Beneath these streets lies a city much older than any cable.

A practical tip: the sign in front of your house counts more than any list. When the ban lasts more than a week, the company must update it every week with the correct dates.

Photo: Fabien Bièvre-Perrin, Taranto, necropoli via Marche, Wikimedia Commons, license CC BY-SA 4.0.

#lavori#rete elettrica#Tre Carrare#Solito#Borgo#corso Italia#via Dante#divieti di sosta#viabilità